NEW QUESTION 27
How is the actual availability of a resource for project assignments calculated?

  • A. Available hours = Free hours - Staffed hours
  • B. Free hours = Staffed hours - Available hours
  • C. Free hours = Available hours - Staffed hours
  • D. Available hours = Staffed hours - Free hours

Answer: C

 

NEW QUESTION 28
What can you use the View Browser app to do?

  • A. Launch analytic cloud stories
  • B. Display custom SAP views irrespective of draft or released status
  • C. Create, edit, and delete CDS views
  • D. Get a list of all available analytical CDS views and their artifacts

Answer: B

 

NEW QUESTION 29
What determines the set of data migration objects available from the Migrate Your Data application?

  • A. The selected business scenarios
  • B. The selected source system
  • C. The selected target fields
  • D. The customer legacy system

Answer: A

 

NEW QUESTION 30
What are the available methods through which you can fill staging tables in the SAP HANA database of the target system? Note: There are 3 correct Answers to this question.

  • A. SAP HANA Smart Data Integration (SDI)
  • B. Customer's ETL tools
  • C. XML templates
  • D. SAP Smart Data Access
  • E. SAP SQL Anywhere

Answer: A,B,C

 

NEW QUESTION 31
Which of the following are KPI cards in Fiori app Resource Management for Projects? Note: There are 3 correct Answers to this question.

  • A. Work Package Utilization
  • B. Resources with Free Capacity
  • C. Average Resource Utilization
  • D. Contingent Resources
  • E. Overbooked Resources

Answer: B,C,E

 

NEW QUESTION 32
In what phase of the SAP Activate methodology do you test the business processes?

  • A. Explore
  • B. Deploy
  • C. Realize
  • D. Prepare

Answer: C

 

NEW QUESTION 33
Which of the following are primary tasks of Project Managers? Note: There are 3 correct Answers to this question.

  • A. Create customer invoice
  • B. Maintain project staffing
  • C. Maintain project billing
  • D. Plan work packages and efforts
  • E. Create billing proposal

Answer: B,C,D

 

NEW QUESTION 34
In which implementation phase do you perform data load preparation?

  • A. Deploy
  • B. Realize
  • C. Prepare
  • D. Explore

Answer: D

 

NEW QUESTION 35
What tasks can the Resource Manager perform through the Fiori apps that are available in the advanced version of Resource Management? Note: There are 2 correct Answers to this question.

  • A. Maintain skills for work items
  • B. Monitor and analyze resource utilization
  • C. Transfer actual working times
  • D. Staff resource requests for project roles

Answer: B,D

 

NEW QUESTION 36
A customer needs detailed customization to the standard forms and email templates. What solution should the consultant propose?

  • A. Create a custom UI with the Custom Fields and Logic app
  • B. Use the Adobe Livecycle Designer tool to edit a standard template
  • C. Use the corresponding configuration items to modify elements of the form template
  • D. Use the Output Management apps to customize a standard template

Answer: B

 

NEW QUESTION 37
Which of the following business roles are required to analyze the Margin & Work Analysis for Projects? Note:
There are 2 correct answers to this question.

  • A. Analysis Accountant
  • B. Margin Analyst
  • C. Project Manager - Commercial Services
  • D. Analytics Specialist

Answer: C,D

 

NEW QUESTION 38
Which tasks can the Project Manager perform through Fiori app Release Billing Proposals - Due Today?
Note: There are 2 correct Answers to this question.

  • A. Create billing document
  • B. Delete billing proposals
  • C. Postpone billing proposal
  • D. Edit billing proposals

Answer: C,D

 

NEW QUESTION 39
Under which circumstances would the Resourse Manager receive multiple resource requests for the same project or work package? Note: There are 2 correct Answers to this question.

  • A. A work package can contain more than one request for the same project role.
  • B. A resource request can represent multiple project roles that need to be staffed.
  • C. A resource request for a work package may require multiple resources.
  • D. A project usually consists of multiple work packages, which may require multiple roles.

Answer: A,C

 

NEW QUESTION 40
What SAP solution provides collaboration capabilities to increase workforce productivity?

  • A. SAP Concur
  • B. SAP Jam
  • C. SAP SuccessFactors Employee Central
  • D. SAP Fieldglass

Answer: C

 

NEW QUESTION 41
Which processes are covered in the SAP Best Practices Internal Project Management - Project-Based Services (1A8) scenario? Note: There are 2 correct Answers to this question.

  • A. Perform period-end closing activities
  • B. Maintain work package staffing
  • C. Capture service units
  • D. Perform margin analysis

Answer: A,B

 

NEW QUESTION 42
Which apps can be accessed from the KPI cards in the advanced version of Fiori app Resource Management for Projects? Note: There are 2 correct Answers to this question.

  • A. Manage Project Assignments
  • B. Manage Resource Requests
  • C. Manage Resource Utilization
  • D. Manage Project Staffing

Answer: C,D

 

NEW QUESTION 43
Which procurement subprocesses are covered by the SAP Best Practices Service and Material Procurement - Project-Based Services (J13) scenario? Note: There are 2 correct Answers to this question.

  • A. Procurement of direct materials
  • B. Procurement of consumable materials
  • C. Procurement of consigned inventory/subcontracting
  • D. Procurement for third-party order processing

Answer: B,D

 

NEW QUESTION 44
Which parameters are mandatory to schedule a revenue recognition job in Fiori app Run Revenue Recognition - Projects? Note: There are 3 correct Answers to this question.

  • A. To period
  • B. Company code
  • C. Ledger
  • D. WBS Element
  • E. Project Definition

Answer: A,B,C

 

NEW QUESTION 45
Based on the SAP Activate methodology, which activities must you perform in the Explore phase? Note:
There are 2 correct Answers to this question.

  • A. Configure the organizational structure and chart of accounts in the system
  • B. Use the Quality system to demonstrate SAP Best Practices processes
  • C. Use the Starter system to demonstrate SAP Best Practices processes
  • D. Conduct the Fit-to-Standard workshops to enable customers and identify gaps

Answer: C,D

 

NEW QUESTION 46
......

Prepare for your SAP certification with the updated SureTorrent C-S4CPS-2202 exam questions: https://drive.google.com/open?id=1VXeAbLo8JLB7bzYIK2qWKWuAAvxv_Nxo