NEW QUESTION 81
For which objects can you revaluate activities and business processes at actual prices? There are THREE correct answers for this question
- A. Work centers
- B. Profit centers
- C. Cost centers
- D. Profitability segments
- E. Work breakdown structure elements
Answer: B,D,E
NEW QUESTION 82
What are some of the characteristics of internal order planning? 2 answers
- A. Availability control is checked
- B. Multiple versions are allowed
- C. Costs are entered
- D. Tolerance limits are defined
Answer: B,C
NEW QUESTION 83
You perform a settlement with a primary cost account which is different from the cost account you used to post the original expense. Which object is a valid receiver for the settlement?
- A. Cost center
- B. Fixed Asset
- C. Internal order
- D. WBS element
Answer: B
NEW QUESTION 84
What master data objects can you set up using time-based fields?
- A. Standard hierarchies
- B. Cost centers
- C. Activity types
- D. Statistical key figures
Answer: B,D
NEW QUESTION 85
In your company, you tend to go through many reorganizations leading to extra master data maintenance work. Which grouping functionality can save you time maintaining profit center groups?
- A. Creating multi-dimension sets
- B. Configuring derivation rules
- C. Copying groups with suffix
- D. Defining flexible hierarchies
Answer: C
NEW QUESTION 86
At which level do you define the valuation method for result analysis?
- A. Company code
- B. Operating concern
- C. Sales organization
- D. Controlling area
Answer: D
NEW QUESTION 87
What do you use to map the primary cost component split to the production cost component structure?
- A. Assignment scheme
- B. Transfer structure
- C. Allocation structure
- D. Cost Component groups
Answer: D
NEW QUESTION 88
How do you maintain number intervals/ranges in Controlling?
- A. By document type
- B. By company code
- C. By business transaction
- D. By posting key
Answer: C
NEW QUESTION 89
In the product Cost by Order component, what does the system calculate depending on the order status? 1 answer
- A. WIP at target costs or variances
- B. Both WIP and variances or only variances
- C. WIP at planned costs or variances
- D. WIP at actual costs or variances
Answer: D
NEW QUESTION 90
Why would you use manual cost allocation in Controlling? 2 answers
- A. To allocate costs using an allocation cycle
- B. To run simple allocations of actual data
- C. To run simple allocation of plan data
- D. To correct secondary postings
Answer: B,D
NEW QUESTION 91
What are some of the characteristics of Profit Center Accounting in SAp S/4HANA? 2 answers
- A. It can be used in the settlement rule for internal orders
- B. It can be used with period and/or cost of sales accounting
- C. It is integrated in the universal journal
- D. It is possible to derive the profit center from the segment in configuration
Answer: B,C
NEW QUESTION 92
What are the benefits of using valuated sales order stock compared to non-valuated sales order stock?
There are TWO correct answers for this question
- A. Simplified inventory value determination
- B. Production order settlement to sales order
- C. Production cost calculation
- D. Combined quantity and value flow analysis
Answer: A,D
NEW QUESTION 93
Which objects are predifined characteristics in SAP S/4HANA? 3 Answers
- A. Plant
- B. Region
- C. Product Category
- D. Company Code
- E. Controlling Area
Answer: A,D,E
NEW QUESTION 94
Which costs exist in SAP S/4HANA? 2 answers
- A. Primary costs without G/L account
- B. Primary costs with G/L account
- C. Primary costs without G/L account
- D. Secondary costs with G/L account
Answer: B,D
NEW QUESTION 95
Which process determines the target costs of the cost object in a product cost by order scenario?
- A. Accrual calculation
- B. Actual costs calculation
- C. Variance calculation
- D. Work in process (WIP) calculation
Answer: C
NEW QUESTION 96
Which order status is relevant for creating work in process (WIP) calculations when you use Product Cost by Order (PCO)?
- A. Technically completed
- B. Created
- C. Delivered
- D. Partially released
Answer: D
NEW QUESTION 97
Independent from the cost object, which parameters are always contained in a costing variant? There are TWO correct answers for this question
- A. Transfer control
- B. Valuation variant
- C. Costing type
- D. Reference variant
Answer: B,C
NEW QUESTION 98
Which main elements do you configure for the overhead costing sheet? There are TWO correct answers for this question
- A. Credit key
- B. Revaluation rate
- C. Allocation structure
- D. Overhead rate
- E. Calculation base
Answer: D,E
NEW QUESTION 99
What can you do with statistical internal orders ?
- A. Apply overhead rates to the internal order
- B. Transfer posting to another internal order
- C. Settle costs to a cost center
- D. Simultaneously post to a cost center
Answer: D
NEW QUESTION 100
Which management accounting currencies can you use for evaluation when you use crosscompany- cocie cost accounting? There are THREE correct answers for this question
- A. Company code currency
- B. Controlling area currency
- C. Reference currency
- D. Object currency
- E. Transaction currency
Answer: A,B,D
NEW QUESTION 101
Which views can you use to analyze the costing results within the costing run tool? There are THREE correct answers for this question
- A. Costing levels report
- B. Variance report
- C. Work in progress report
- D. Analysis report
- E. Material list report
Answer: A,D,E
NEW QUESTION 102
You are setting up costing-based Profitability Analysis for your organization. How do you configure the different market segments?
- A. As characteristics
- B. As key figures
- C. As value fields
- D. As divisions
Answer: A
NEW QUESTION 103
Which objects do you use when you assign costs and revenue to the value fields in costingbased CO- PA?
- A. Transfer structure
- B. Allocation structure
- C. Overhead group
- D. Allocation template
Answer: B
NEW QUESTION 104
What do you do to create a primary cost component split? There are TWO correct answers for this question
- A. Run an activity price calculation
- B. Use the cost splitting tool on cost centers
- C. Assign a cost component structure to the CO-version
- D. Enter split activity prices manually
Answer: A,C
NEW QUESTION 105
......