NEW QUESTION # 22
In the Product Cost by Order process, what does the system calculate depending on the order status?
- A. WIP at percentage of completion (PoC) method or variances
- B. Both WIP and variances
- C. WIP at target costs or variances
- D. WIP at actual costs or variances
Answer: D
NEW QUESTION # 23
Which of the following steps are part of the procedure to update the standard price of the material? Note: There are 2 correct answers to this question.
- A. Mark the cost estimate.
- B. Split the costs.
- C. Archive the cost estimates.
- D. Release the cost estimate.
Answer: A,D
NEW QUESTION # 24
Which statement best describes the Query Browser for reporting?
- A. It is the frontend used to define reports in Analysis for Office.
- B. It is a desktop browser that integrates with SAP S/4HANA.
- C. It is a design studio app that comes as standard SAP Fiori content.
- D. It is available as an additional license product in SAP S/4HANA.
Answer: B
NEW QUESTION # 25
What are some of the objectives of Profitability Analysis? Note: There are 2 correct answers to this question.
- A. Allow the company to determine if the sales force achieved their contribution margin goals.
- B. Allow the company to determine standard costs and revenues according to the period accounting method.
- C. Provide the company with a detailed view of its financial statements by areas of responsibilities.
- D. Provide the company with information on the performance of its market segments.
Answer: A,D
NEW QUESTION # 26
You create a new profit center. Which company code(s) is it assigned to by default?
- A. All company codes where profit center accounting is activated.
- B. All company codes to which the profit center standard hierarchy is assigned to.
- C. All company codes maintained in your authorization profile.
- D. All company codes within the controlling area.
Answer: D
NEW QUESTION # 27
What master data objects can you set up using time-based fields? Note: There are 2 correct answers to this question.
- A. Statistical key figures
- B. Activity type
- C. Cost element
- D. Cost centers
Answer: B,D
NEW QUESTION # 28
In the material master record there are three planned prices: ""Planned price 1"", ""Planned price 2""and""Planned price 3"". What do you use them for?
- A. To valuate goods movement
- B. To update the standard price during the release of a standard cost estimate
- C. To valuate the materials in cost estimates
- D. To valuate material stocks
Answer: C
NEW QUESTION # 29
You want to determine which operations of the routing should be considered in a product cost calculation. How do you do this? Note: There are 2 correct answers to this question.
- A. By marking the cost indicator in the control key assigned to the operation
- B. By marking the Relevance to Costing indicator in the operation
- C. By assigning a cost center to the work center in the operation
- D. By defining a usage key in the header of the routing.
Answer: A,B
NEW QUESTION # 30
What are some of the characteristics of SAP Core Data Services (CDS) views? Note: There are 3 correct answers to this question.
- A. CDS views duplicate data for reporting efficiencies.
- B. CDS views have ready-to-use content.
- C. CDS views are considered system modifications.
- D. CDS views have no latency.
- E. CDS views support authorization.
Answer: B,D,E
NEW QUESTION # 31
You want to create cost centers for your company. What is the prerequisite to build an organizational structure for overhead cost controlling?
- A. Profit center
- B. Person responsible
- C. Standard hierarchy top node
- D. Cost center categories
Answer: C
NEW QUESTION # 32
You are setting up a direct internal activity allocation in SAP S4/HANA. What is valid receivers for the activity? Note: There are 3 correct answers to this question.
- A. Internal order
- B. Profit center
- C. General ledger account
- D. Sales order item
- E. WBS element
Answer: A,D,E
NEW QUESTION # 33
Which statements best describes a single cost center standard hierarchy?
- A. It is a structure to which all the cost centers within a controlling area are assigned.
- B. It is a structure to which all cost center groups created within an operating concern are assigned.
- C. It is a structure to which all the cost centers within an operating concern are assigned.
- D. It is a structure to which all cost center groups create for a controlling area are assigned.
Answer: A
NEW QUESTION # 34
You want to prevent reporting extreme periodic fluctuations in your P&L statement. Which Management Accounting activity should you choose to help spread irregular expenses throughout the fiscal year?
- A. Budget availability control
- B. Accrual calculation
- C. Periodic reporting
- D. Indirect activity allocation
Answer: B
NEW QUESTION # 35
Which setting in the cost center master data do you use to assign the same attributes to similar cost center?
- A. Standard hierarchy node
- B. Cost center type
- C. Object class
- D. Cost center category
Answer: D
NEW QUESTION # 36
What parameters can you set up when defining order types?
- A. Allow revenue postings.
- B. Define document type.
- C. Define source structure.
- D. Define default parameters for master record fields.
Answer: A,D
NEW QUESTION # 37
......